Yes, concrete cracks, but an attempt should be made to anticipate where the cracks will occur by placing control joints (gaps between concrete sections) in the concrete. Control joints are dug into the wet concrete while the finish is put on, or cut in later with a concrete saw. You’ve seen the control joint before; they are the gaps that create the “blocks” in the sidewalk or driveway.
If the joint is put in at the finish stage, a notched trowel is used to dig a groove in the wet slab. This groove needs to be about an inch deep to ensure that the crack takes place there and not in a random location. Control joint spacing is determined by the width of the slab, but joints should never be placed more than twelve feet apart. On a sidewalk that is four feet wide, control joints should be placed every four feet.
Some concrete slabs need to be separate by design. Where slabs have been poured at different times and have different uses, a special material needs to keep the sections independent. In some areas such as where the concrete driveway meets the garage, an asphalt impregnated fibrous material (tar paper) is installed between the two materials before the pour to completely separate the slabs.
Cracking will take place in slabs and poured concrete walls, but how do you know when a crack is compromising the strength or performance of the concrete?