Setting Grade

Once you are confident that the house will be built in the correct location on the lot, you need to understand how high the house will sit on the lot. A mistake here can be a costly one for both you and the builder. The way the house sits on a lot can affect:

• drainage • pitch of driveway • usefulness of the lot • appearance from the street • sewer connection

The biggest issue is drainage — both for the water runoff and sewer placement. If your house sits too low on the lot (i.e. the hole for your foundation is dug too deep), especially in relation to your neighbors, storm water run-off will flow down toward your house. Even if you don’t have a basement to worry about flooding, your lot can turn into a swamp if there is not proper fall

(or slope away) and a storm water management plan. Water management must begin early; it is usually not something that can be corrected later. If the top of your foundation wall will not be as high as your neighbor’s, make sure there is enough space between houses to create a swale (“V” shaped channel graded to divert water) for drainage. The builder also needs to be aware of the sewer location because most all sewers work on gravity. Therefore, the connection to the house must be at the right level (i.e. the pipe must connect to the house at a higher elevation than where it connects to the sewer line in the street).

After the lot is cleared, but before the foundation is dug, the decision on the depth of the hole is made. For the purpose of this example, we’ll assume the house has a basement, but the same calculation is used for a crawl space. The decision is made from several factors but is made by knowing what the height of the basement wall will be. A benchmark height marking the top of the basement wall, crawl space, or slab will be marked on a stake or tree so that the excavator can reference it. The hole depth is calculated by adding up the depth of the foundation and anything that will rest on top of it and then subtracting for the desired wall height above the current grade.

Example for calculating hole depth: basement wall- 8’ foundation- 1’ desired height above existing grade: 1’ (basement wall height + foundation depth) – height above grade= 8’ hole